A group of retired civil servants has urged the Indian government to abandon the proposed 1,750-megawatt Demwe Lower Hydroelectric Project in Arunachal Pradesh, warning that the dam would devastate a globally significant rainforest, threaten a tiger reserve, and displace indigenous communities.

Ecological Stakes

The Demwe project envisions a concrete gravity dam across the Lohit River, a major tributary of the Brahmaputra. According to the letter, the project would require diverting 1,416 hectares of forest land and felling approximately 43,000 trees in an ecologically sensitive evergreen rainforest. The submergence zone alone would cover 1,590 hectares.

What is a peaking power plant? Unlike dams that provide steady baseload power, peaking plants store water and release it in short bursts to meet peak electricity demand. This creates dramatic, daily fluctuations in downstream flow — essentially manufacturing artificial floods and droughts that disrupt aquatic ecosystems, sediment transport, and riverine livelihoods.

The letter highlights that the dam site and its submergence area would extend to within 50 metres of the Kamlang Tiger Reserve and intrude into its designated eco-sensitive zone. These zones are legally mandated buffers where industrial activity is restricted to protect wildlife corridors and habitat integrity. Encroachment this close to a protected area undermines the very purpose of the reserve network.

Social Costs

Beyond environmental metrics, the former bureaucrats emphasize the human dimension. Tribal groups, student unions, and local residents have sustained protests against the project, framing it as a threat to ancestral lands and cultural survival. The letter notes "mass displacement and the erasure of their culture" as central grievances.

What is at stake for local communities? Arunachal Pradesh is home to numerous indigenous tribes with distinct languages, traditions, and land-use practices. Large dams typically submerge villages, agricultural land, and sacred sites, forcing relocation to areas where traditional livelihoods — shifting cultivation, fishing, forest gathering — are no longer viable. The resulting cultural dislocation often persists for generations.

The resistance also invokes the Parashuram Kund pilgrimage site, a Hindu religious destination on the Lohit River that would be affected by the project. During 2012–13, local opposition to protect this site contributed to the project's stalling, alongside financial constraints. The letter argues that the project has been "pursued since 2011 by different governments, in spite of the havoc it will create on endemic wildlife as well as on tropical rainforests and people."

Governance Failures

A core demand in the letter targets the Standing Committee of the National Board for Wild Life (NBWL), the apex body that clears projects in protected areas and eco-sensitive zones. The signatories allege that the committee has functioned as "an administrative arm of the government" rather than an independent guardian of wildlife. They urge the Union government to reconstitute the committee with non-government experts.

How does the NBWL work? The National Board for Wild Life, chaired by the Prime Minister, sets policy for wildlife conservation. Its Standing Committee evaluates specific projects — like dams, highways, or mines — that require forest or wildlife clearances. Critics have long argued that its composition, dominated by government nominees, creates a conflict of interest when assessing state-backed infrastructure projects.

The letter's call for expert-led reform reflects a broader debate about environmental governance in India: whether regulatory bodies can withstand political pressure to fast-track strategic projects in ecologically fragile regions like the Northeast.

Historical Context

The Demwe Lower project is not an isolated case. The letter references the Upper Siang dam project, another mega-hydro scheme in Arunachal that has faced similar opposition. Many have stalled due to geological risks, seismic vulnerability, financing gaps, and sustained local resistance.

The Constitutional Conduct Group's intervention adds institutional weight to these protests. As former administrators, the signatories bring insider knowledge of how clearances are granted, how environmental impact assessments are often diluted, and how public hearings can be perfunctory. Their letter frames the Demwe project as a test case for whether India's environmental laws — and the bodies that enforce them — can prevail over development imperatives.

The Path Forward

The letter concludes with three demands: halt the "disastrous" project, protect the ecological and geographical integrity of the Lohit basin, and support local communities instead of subjecting them to "police violence during clashes." The latter reference points to a pattern of security-force deployment against anti-dam protesters in the Northeast.

For the government, the choice is stark. Proceeding with Demwe Lower would signal that strategic energy targets and investment commitments outweigh constitutional safeguards for forests, wildlife, and tribal rights. Scrapping it — or at minimum, subjecting it to a genuinely independent review — would affirm that ecological limits and social consent are non-negotiable.

As climate change intensifies pressure to decarbonize, the tension between renewable energy expansion and biodiversity protection will only sharpen. The Demwe decision may set a precedent for how India navigates that tension in its most vulnerable landscapes.

Was this clear?

check_circleVerified by Official Documents

library_booksSource

public

Scroll.in

24 Nov 2026

Read sourceopen_in_new
funding model
independent commercial media (revenue from advertising, reader subscriptions and grants)
owner
Scroll.in (Scroll Media), an independent digital newsroom founded by Samir Patil

Was the source link correct?

topicRelated Articles